Project Manager: Dorthy Albright, PMP
Business Lead: Mary Ann Szymoniak
Project Documents: Project Charter (.pdf)
| High Level Schedule | |
| Task Description | Due Date |
| "As Is" Model | 5.3.05 |
| Site Visit Planning | 5.20.05 |
| "To Be" Model | 8.25.05 |
| Site Visits | 9.22.05 |
| Strategic Analysis | 9.22.05 |
| Draft Report | 11.2.05 |
| Strategic Planning Report | 3.16.06 |
| Final Report | 4.2.06 |
| Closeout | 5.16.06 |